Marina Enhancement & Community Revitalization Plan

*This content is provided by the City of Isle of Palms for informational purposes only and does not express the opinion of City Staff, City Council, or any individual City official.

The City of Isle of Palms will hold a referendum on November 7, 2017, to ask residents to vote on whether to issue a bond not to exceed $5,500,000 to complete the Marina Enhancement and Community Revitalization Project.

Marina Enhancement and Community Revitalization plan
Approved by City Council on September 26, 2017

Download PDF File 

Marina Existing Conditions and Proposed Improvements 

ISLE OF PALMS MARINA SOURCES AND USES OF FUNDS FROM FY99 - FY17

 

Download PDF File 

Resource documents
Community Informational Meetings

The City of Isle of Palms will host two (2) meetings to provide information to citizens about the proposed Marina Enhancement & Community Revitalization Plan:

  • September 27, 2017 from 4:00 p.m. to 7:00 p.m. - Open House at the Marina, located at Fifty, Forty-First Avenue. 
    • This open house will allow you to walk through the existing Marina site and learn more about the proposed infrastructure improvements and community amenities. The City will provide information about the plan and will be available to answer questions.
  • October 12, 2017 from 5:00 p.m. to 8:00 p.m. - Informational Community Meeting at the Recreation Center, located at Twenty-Fourth, Twenty-Eight Avenue. 
    •  This informational community meeting will provide information about the existing Marina site and the proposed infrastructure improvements and community amenities.

Read the Real Property Committee meeting minutes for the most up-to-date discussion related to the Marina Enhancement & Community Revitalization Plan. 

 
Reverse Chronology
September 26, 2017

City Council unanimously approved the final rendering of the Marina Enhancement and Community Revitalization Plan. 

September 21, 2017

The City sent all Isle of Palms registered voters a Referendum Announcement & Fact Sheet about the proposed Marina plan. 

July 18, 2017

Applied Technology and Management (ATM) will present the latest version of the Marina Redevelopment Plan and associated cost estimate at the Real Property Committee Meeting on Tuesday, July 18, 2017.  

May 16, 2017 

Applied Technology and Management (ATM) presented to the Ways and Means Committee a revised version of the Real Property Committee Scenario for the Marina Redevelopment Plan. The Ways and Means Committee unanimously approved to proceed with this plan, totaling approximately $4,838,000 based on the outline of data presented, recognizing that the Plan is still subject to change, and to do so in a timely fashion to hold a referendum in November 2017.

July 26, 2016

Applied Technology and Management (ATM) presented to City Council a fourth scenario of the Marina Redevelopment Plan. This scenario takes into consideration the feedback received from members of Council, marina tenants, neighbors of the marina and the harbor master of the Dewees Marina related to the third scenario. 

April 28, 2016

Applied Technology and Management (ATM) presented to City Council a third scenario of the Marina Redevelopment Plan that takes into consideration suggestions from the Planning Commission. 

February 23, 2016

Applied Technology and Management (ATM) presented to City Council the Comprehensive Redevelopment Master Plan for the Isle of Palms Marina. Below are the documents that make up the full work product. 

 