IOP Marina Public Dock and Greenspace

On September 22, 2020, City Council voted to create a public dock and greenspace in the space formerly leased to the commercial watersports operation. 

On November 2023, City Council awarded a contract to Truluck for the construction of a new public dock, which will include a 16' wide pier with covered area with benches and swings, a new floating dock with an ADA compliant gangway, kayak and stand-up paddle board launch. 

Construction began on April 2024, and the anticipated completion date is June 1, 2024. 


View the public dock design drawings here

 

Project Funding Source:

$1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX) 

Updates

Update - May 2025

Tuesday, May 13, 2025
  • Parking engineer met with Public Facilities and discussed modifications to the parking layout that will be presented to the restaurant tenants. 

Update - March 2025

Monday, March 10, 2025
  • Dock completed and ribbon cutting was held February 7th.
  • Parking engineer and marina tenants will be invited to future workshop to discuss potential parking layouts for implementation in upcoming winter.

Update - February 2025

Monday, February 10, 2025
  • Dock completed and ribbon cutting was held February 7th. Public Facilities Committee discussed greenspace 2/11/25.

Update - January 2025

Monday, January 13, 2025

Swings for the public dock have been installed and the contractor is finalizing the electrical system and the barriers. Ribbon cutting scheduled for February 7th at 10:30am.

Update - July 2024

Monday, August 12, 2024

IOP Marina Public Dock & Greenspace

  • Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
  • Framing and decking work complete. Gangway being fabricated. Truluck and ATM finalizing floating dock submittal.

 

Update - August 2024

Monday, August 12, 2024

Technical workshop held in March to identify vulnerabilites and establish agreed upon sea level rise projections. Stakeholder meetings held w the Planning Commission and Enviromental Advisory Committee in May. Sea Level Rise Community Engagement Survey released in July and deadline is August 1.

Update - June 2024

Monday, June 17, 2024

IOP Marina Public Dock & Greenspace

  • Framing and decking work in process. Gangway and floating dock submittals under review by ATM - once approved, will be released for fabrication. City waiting on revised completion schedule.

IOP Marin "T" Dock Repairs 

  • Completed 

Marina Dredging - Design and Permitting

  • Work in process. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.

 

Update - May 2024

Monday, May 13, 2024

OP Marina Public Dock & Greenspace

  • Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
  • Pile driving and superstructure construction almost complete. Delay on the floating dock and ADA gangway submittals, due in part to challenges with confirmation of location of subaqueous electrical cable that runs from the IOP to Goat Island near proposed floating dock. Substantial completion date is June 16th but may be pushed.

IOP Marina "T" Dock Repairs

  • Funding Source: $200K Marina Fund 
  • Repairs are near completion 

 

Update - April 2024

Monday, April 08, 2024

IOP Marina Public Dock & Greenspace

  • Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
  • Demolition of public dock began week of 4/1. After demolition, contractor will begin pile driving. Anticipated completion June 1st.

IOP Marina "T" Dock Repairs

  • Funding Source: $200K Marina Fund 
  • Work in progress 

Marina Dredging - Design and Permitting

  • Funding Source: $1.5M FY23 State Budget Allocation
  • Work in progress. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.

Update - February 2024

Monday, February 12, 2024

IOP Marina Public Dock & Greenspace

Contract executed with Truluck Construction. Construction drawings in process. Contractor anticipated to mobilize in March.

IOP Marina "T" Dock Repairs

Removal of electrical and water systems, repairs to fixed pier and floatind dock and installation of fire extinguisher pedestals included in Truluck contract. Tenants requested to extend finger piers in lieu of new electrical and water systems, which requires permit modification from regulatory agencies. ATM provided proposal to City for permit modification assistance and coordination.

Marina Dredging - Design and Permitting

In process. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.

Project Type