Beach Restoration Projects Update

beach restoration project   beach restoration project

 

April 23, 2025

Please note: Only the immediate work area of the beach will be closed for the duration of these projects. The city offers more than 50 beach access paths to enjoy.

 

U.S. Army Corps of Engineers (USACE)

Crews are currently working just north of 3rd Avenue and will continue operations throughout most of the summer.

 

City’s Supplemental Contractor

The project is now halfway complete. Sand placement has been completed from 6th Avenue through 9th Avenue.

  • Sand has also been placed between 4th and 6th Avenues, but grading is still ongoing in that area.
  • Work in the vicinity of 5th and 6th Avenues, extending through Breach Inlet, is expected to be completed within the next two weeks.

 

Wild Dunes Shoal Management 

  • This weekend, crews will move from the Beachwood East area to place sand in the area in front of Seascape and the Ocean Club Villas. This phase is expected to take around ten days to complete.
  • Following that, work will resume in the Beachwood East area and continue until mid-May.

     