Please note: Only the immediate work area of the beach will be closed for the duration of these projects. The city offers more than 50 beach access paths to enjoy.
For your safety, please stay clear of the construction area and equipment.
May 13, 2025
U.S. Army Corps of Engineers (USACE)
USACE work is progressing, and sand is currently being deposited in the 300 block of Ocean Blvd. Work is expected to continue throughout most of the summer.
City’s Supplemental Contractor
This project is complete. Sand from the USACE project has been moved and graded to create a new dune from 9th Avenue to Breach Inlet.
Wild Dunes Shoal Management
Approximately 90,000 cubic yards of sand have been placed in the Ocean Club, Seascape, and Beachwood East areas. Crews will return to Beachwood East to place an additional 30,000 cubic yards of sand. This week, the contractor will assess whether more sand is needed in the area around Ocean Club. The project remains on track for completion this week.