Funding Source:
$20K - Beach Preservation Fund
Updates
Update - July 2025
Tuesday, July 08, 2025
- In June, the City received the permit from the SC DES, but still has not received a permit from USACE.
Update - May 2025
Tuesday, May 13, 2025
- ATM responded to comments and provided sediment testing results to USACE in April.
Update - April 2025
Tuesday, April 08, 2025
Several comments were received in the Federal permit process and responses are being prepared to resubmittal the week of April 7th.
Update - March 2025
Monday, March 10, 2025
Federal permit applications are out for public comment. Will respond to any comments that are received.
Update - January 2025
Monday, January 13, 2025
Federal permit applications have been submitted.
Update - August 2024
Monday, August 12, 2024
Pre-application meeting with the USACE on Sept 17.